Use the Work Plan
A project’s Work Plan lists its phases and sub-phases in WBS order, each with its tickets and hours. Open it from a project tab, or click the project or phase on a project ticket to open the project on its Work Plan with that ticket in focus. How to open projects, and who can, is in Work with projects.
What you can change follows your ConnectWise security role for projects. Changes are made with your own ConnectWise access, and when ConnectWise refuses one MTX shows its reason and changes nothing. A closed project’s phases cannot be changed.
When you start work on a ticket from the Work Plan, MTX returns to that project’s Work Plan after you finish.
Phases
Section titled “Phases”- Add Phase adds a top-level phase; Add Sub-Phase on a phase row adds one beneath it. Only a description is needed; ConnectWise gives it its WBS code. Offered when your role can add phases.
- Rename changes a phase’s description and nothing else.
- Delete removes a phase that has no sub-phases and no tickets, after you confirm by selecting D, E and L.
Click a phase to open its details beside the Work Plan: description, status, parent phase, deadline, milestone and bill-separately flags, and notes, with its WBS code, hours and scheduled dates read-only. If your role can edit project finance, you can also change whether it bills time, expenses and products. A sub-phase cannot be moved back to the top level: ConnectWise does not allow it. ConnectWise may renumber WBS codes after a move, and the Work Plan shows the new ones.
Apply Template adds a ConnectWise project template’s phases and tickets after the project’s own, once you confirm how many it will add. It is offered when your role can add phases and project tickets, and changes nothing that is already there.
Columns
Section titled “Columns”Besides its usual columns, the Work Plan can show each phase’s and ticket’s scheduled start and finish, and each ticket’s owner and resources. Hide the ones you do not need under Columns; MTX remembers your choice on this device.
Change several at once
Section titled “Change several at once”Tick tickets or phases, or tick the header to select every row shown. Ticking a phase does not select its tickets. The bulk-action bar replaces Add Phase, Apply Template and Columns while anything is selected, and offers only what your role allows:
| For | Actions |
|---|---|
| Tickets | Set the status (from the project board’s statuses), priority, type or owner; add a Cc address, skipping tickets that already have it; move them to the end of another phase of the project; delete them. |
| Phases | Set the status; delete the empty ones. |
Deleting asks you to confirm with D, E, L, naming how many will be deleted. ConnectWise does not delete a project ticket that has time entries, or a phase with sub-phases or tickets.
MTX changes the items one at a time, in Work Plan order, and does not stop at the first refusal. At the end it shows how many succeeded and lists each one refused, with ConnectWise’s reason. You can cancel a run; the items not yet reached are listed. One run changes at most 100 items.
Reschedule on the Timeline
Section titled “Reschedule on the Timeline”The Timeline view of a project tab is a Gantt chart of the Work Plan:
- a ticket with an estimated start and a due date is a bar; a ticket without them has no bar;
- a phase is a bar from its earliest to its latest dated ticket, and a milestone phase is a marker at its deadline;
- an arrow joins each predecessor to its ticket, and a line marks today.
Switch between week and month, and between estimated dates and scheduled dates (from schedule entries). Each row shows its budget and actual hours, marked when over budget. Click a ticket to open it.
If your role can change project scheduling, you can, in estimated dates:
- drag a ticket’s bar to move its start;
- drag the end of its bar to change its duration in working days;
- draw a link from a ticket or phase to a ticket to make it the ticket’s predecessor, or remove a link.
ConnectWise then reschedules the tickets that depend on it, and MTX highlights the ones it moved until your next change. Moving the start of a ticket that has a predecessor removes the predecessor in ConnectWise, so MTX asks first. A link that would make a ticket its own predecessor is refused. The scheduled-dates view is read-only.
A project ticket’s scheduling
Section titled “A project ticket’s scheduling”A project ticket’s properties show Estimated Start, Duration (working days, at least 1), Due Date, Predecessor (another ticket or phase of the project) and Lag, with whether the lag counts non-working days. If your role can change project scheduling, you can edit them there too. ConnectWise may work the due date out from the start and duration; MTX shows the date ConnectWise keeps. The Work Plan, the Timeline and other open tickets of the project show the new dates without a reload.